樹木施工期間保護計畫 Tree Protection Requirements During Construction
Tree Protection Requirements During Construction
The area around the tree, extending up to a
distance equal to 10 times the trunk diameter, is considered the Tree
Protection Zone (TPZ) because it provides most of the elements the tree needs
to survive and remain stable. The following activities are prohibited within
the TPZ unless approved by the City Arborist (SMMC 13.40.080#(b)(5)):
(A) Excavation, grading, soil deposit,
drainage, and leveling.
(B) Disposal or depositing of oil,
gasoline, chemicals, paints, solvents, or other materials within the TPZ or in
drainage channels, swales, or areas that may lead to the Dripline.
(C) Soil Compaction from heavy machinery
and vehicles, storage of materials, structures, paving, etc.
(D) Trenching or excavation to provide
irrigation, utility lines, services, pipe, drainage, or other improvements
below grade.
(E) Storage of any materials or equipment
of any kind.
(F) Parking or driving vehicles or
self-propelled equipment.
Tree Protection Plan
If construction activities cannot be kept
outside of the TPZ of protected trees, a Tree
Protection Plan from an ISA Certified Arborist will be required.
Construction activities mean building, demolition, grading, excavation, or
paving, but also include any work that may not be shown on the plans, like
storing or staging of materials, site access, parking, placement of temporary
structures, debris disposal, additional excavation, landscaping, etc. (SMMC
13.40.030#(g)).
It is the responsibility of the Applicant
and the Project Arborist to verify the requirements of a TPP and ensure that
all submitted information is consistent to prevent delays. Use the Arborist
Report and Tree Protection Plan Checklist for assistance.
When the TPP is sufficient to prevent harm
from foreseeable construction activities, it shall be approved along with the
construction plans submitted for revision. However, a building permit will not
be issued until tree protection is installed to ensure that no trees are
damaged.
The approved construction plans shall
include all protected trees with the proposed protection measures drawn at
scale. Additionally, the last version of the Arborist Report and TPP must be
inserted in the plans for reference (SMMC
13.40.080#(b)(4)). Important elements to be included are as follows:
- All Protected trees identified with the same number or tag used
in the Arborist report and TPP. Trees proposed to be removed shall be
marked with an "X" or ghosted out.
- TPZs drawn to scale around all trees impacted by development
(including neighboring trees and street trees if applicable).
- Accurate location of fencing using dash-lined symbology.
- Accurate location of trunk wraps and root protection when
fencing is not feasible.
- The location of areas of hand excavation (or other types like
pressurized air, or water).
- The location of areas or specific activities where monitoring
by the Project Arborist is needed.
Sample of an Arborist Report Included in
the Plan Set
Tree protection measures must be installed
before commencing construction work, including activities such as demolition or
site preparation. A building permit cannot be issued until it is verified that
protection measures are properly installed. Failing to comply with the approved
TPP is illegal and may result in stop-work orders, Protected tree violations,
and penalties as described in SMMC
13.40.160.
Approved Protective Measures
The following are the approved protective
measures in the City. These detail sheets can be downloaded and inserted
directly into the project plans from this link.
Type I Complete Protective Fencing
Fencing shall consist of chain link fence
(6 feet high), mounted on galvanized iron posts wit 2 inches in diameter. Each
post must be driven into the ground at least 2 feet deep, no more than 10 feet
apart. The fence shall enclose the entire TPZ of the tree(s) to be protected
throughout the life of the construction project.
Type II Partial/Reduced Fencing
The fence encloses part of the TPZ but the
soil and root zone are protected with root buffers or existing hardscape not
planned to be demolished. For trees situated within the street planting strip,
only the planting strip and yard side of the TPZ shall be enclosed with the
required chain link fencing to provide public use of the street and sidewalk.
Type III Trunk Wrap
(to be used with Root Buffer when
construction activities cannot be kept outside of the TPZ)
Wrap the trunk with orange plastic fencing
for buffering (2" thick). Overlay orange plastic fencing with 2-inch thick
wooden slats bound securely by two layers of additional orange fencing (slats
shall not be allowed to dig into the bark). During installation, use caution to
avoid damaging any branches. Major limbs may also require wrapping. Straw
wattle can be used as an alternative material. For this purpose coil the straw
wattle around the lowest 6' of the trunk and secure it with a double layer of
orange fence or similar material.
Type IV Root Buffer
(to be used with Trunk Wrap when
construction activities cannot be kept outside of TPZ)
The root buffer shall consist of secured
geotextile material covering the area to be protected. Cover the geotextile
material with 4 to 6 inches of clean wood chips. Securely install 3/4-inch
plywood over the wood chips. The root buffer shall be installed and removed
without wheeled equipment touching exposed soil. This means some or all the
work should be done by hand.
Monitoring and Compliance
Periodic monitoring is required to verify
the project's compliance with the TPP. An estimated schedule of inspections by
the Project Arborist will be required as a condition of approval for
construction projects. After each inspection, a letter documenting the
condition of trees and/or reporting any damages must be submitted to the
Building Division.
施工期間樹木保護要求
樹木周圍區域,延伸至相當於樹幹直徑 10 倍的距離,稱為「樹木保護區(Tree Protection Zone, TPZ)」。此區域提供樹木生存與穩定所需的大部分條件。
除非經市府樹藝師(City Arborist)核准(依 SMMC 13.40.080#(b)(5)),否則 TPZ 內禁止從事以下行為:
(A) 挖掘、整地、回填土壤、排水作業及地面整平。
(B) 在 TPZ、排水通道、溝渠或可能流至樹冠滴水線(Dripline)之區域,傾倒或棄置油類、汽油、化學品、油漆、溶劑或其他物質。
(C) 因重型機具、車輛、材料堆放、設施或鋪面造成土壤壓實。
(D) 為設置灌溉、管線、公共設施、排水或其他地下工程而進行開挖或溝渠作業。
(E) 任何形式之材料或設備堆放。
(F) 車輛或自走式機具之停放或行駛。
樹木保護計畫(Tree Protection Plan, TPP)
若施工活動無法完全避開受保護樹木之 TPZ,則必須由國際樹藝學會認證樹藝師(ISA Certified Arborist)提出樹木保護計畫(TPP)。
施工活動包含但不限於:建築、拆除、整地、開挖、鋪面工程,以及圖面未顯示之作業,如材料堆放、施工動線、停車、臨時設施設置、廢棄物處理、額外開挖、景觀工程等(SMMC 13.40.030#(g))。
申請人與專案樹藝師須負責確認 TPP 之要求與內容一致性,以避免審查延誤。可參考樹藝報告及樹木保護計畫檢核表。
當 TPP 足以防止可預見之施工影響時,將與建築計畫一併核准。但在完成樹木保護措施設置前,不會核發建照。
施工圖說應包含內容
核准之施工圖須包含所有受保護樹木及其保護措施(依比例繪製),並納入最新版樹藝報告及 TPP(SMMC 13.40.080#(b)(4))。內容包含:
- 所有受保護樹木須與樹藝報告相同編號或標記
- 擬移除樹木應以「X」或淡化方式標示
- 所有受影響樹木之
TPZ 範圍(含鄰地與行道樹)
- 圍籬位置(以虛線表示)
- 樹幹包覆及根系保護位置(若無法設置圍籬)
- 人工開挖或特殊開挖位置(如氣壓、水刀)
- 需由專案樹藝師監測之區域或作業
施工前要求
所有樹木保護措施須於施工(含拆除或整地)前完成設置。未確認保護措施完成前,不得核發建照。
未依核准之 TPP 執行屬違法行為,可能導致停工命令、違規裁罰及相關處分(依 SMMC 13.40.160)。
核准之保護措施
以下為核准之樹木保護方式,可直接納入施工圖說:
類型 I:完整圍籬保護(Type I)
- 使用 6 英尺高之鍊條圍籬(chain
link fence)
- 鍍鋅鋼柱直徑 2 英吋
- 柱基需打入地面至少
2 英尺
- 柱距不超過 10 英尺
- 圍籬須完整包覆
TPZ,並維持至施工完成
類型 II:部分圍籬保護(Type II)
- 僅圍護部分 TPZ
- 根系區透過根部緩衝或既有鋪面保護
- 若為行道樹,僅需圍設種植帶與庭院側,以維持公共通行
類型 III:樹幹包覆(Trunk Wrap)
(需搭配根系緩衝使用)
- 使用約 2 英吋厚之橘色塑膠網包覆
- 外層加設 2 英吋厚木板條,再以雙層塑膠網固定
- 不得壓入樹皮
- 必要時連同主枝包覆
- 可用稻草束(straw
wattle)替代,包覆樹幹下方約 6 英尺
類型 IV:根系緩衝(Root Buffer)
(需搭配樹幹包覆使用)
- 鋪設固定之不織布(geotextile)
- 上覆 4–6 英吋木屑
- 再鋪設 3/4 英吋夾板
- 設置與拆除過程不得使用機具直接接觸土壤(需人工施作)
監測與合規
須定期由專案樹藝師進行監測,以確認施工符合 TPP。
核准條件將包含檢查時程。每次檢查後,須提交報告至建管單位,記錄樹木狀況及是否有損傷。
資料來源:
https://www.cityofsanmateo.org/4757/Tree-Protection-Requirements-During-Cons









0 意見:
張貼留言